Gier-Sand Creek Drain
| Petition Circulator | |
| Scott & Tammy Cremeans | |
| 2979 West Gier Road Adrian MI, 49221 |
![]() |
||
| Large
PDF (1.3 Mb) Aerial |
DWF
[?] |
|
STATUS OF PROJECT
~ July 11, 2008 Application & Petition provided to Scott & Tammy Cremeans.
~ July 14, 2008 Application & Petition returned.
~ July 30, 2008 Application Signers checked for validity.
~ 39 signatures on the application, 33 valid signatures.
~ August 5, 2008 received Treasurers Certificate for application signers.
~ August 18, 2008 8 - Engineering Proposals received to perform study.
Study costs range $3,850.50 - $9,850.00
~ September 9, 2008 Charter Township of Madison Board Meeting.
~ September 12, 2008 Charter Township of Madison Board Meeting.
~ January 2009 Study completed by Fitzgerald Henne & Associates, Inc. Consulting Engineers.
~ February 26, 2009 7:00 PM Board of Determination on the Petition at the
Charter Township of Madison Hall.
~ March 23,
2009 Lenawee County Clerks Office Contacted and No Appeals filed on
Determination of Necessity of Petition.
~ May 12,
2009 Contract with Fitzgerald Henne & Associates, Inc. Consulting
Engineers Signed to Perform final Engineering & Design, and installation of 3
Monitoring Wells.
~
June 5, 2009 Three Monitoring Wells Installed.
~ September
10, 2009 Bid Opening for Construction of Drain at Lenawee County Drain
Commissioners Office.
~ September
17, 2009 Day of Review of Apportionments at the Office of the Lenawee County
Drain Commissioner.
~ September
23, & 29, 2009 Notice of Appeals and Application for a Board of Review were
filed with the Lenawee County Probate Court.
~ October 2,
2009 the Lenawee County Probate Court, Honorable Appointed a Three Member
Board to Hear the Apportionment Appeals.
~ October 7,
2009 Board of Review meeting at Lenawee County Drain Commissioners Office.
~ October 16,
2009 Board of Review meeting at Lenawee County Drain Commissioners Office Appeal
Resolved.
~ November 6,
2009 Preconstruction Meeting with Jule Swartz & Sons Excavating Inc., Contractor
for Construction.
~
November 18, 2009 Construction on Drain started.
~ February 26, 2010 Contractor has Tile Installed, Restoration to be Performed in the Spring of 2010.
|
Downloads
|
Gier-Sand Creek
Application Signers
Summary of Gier-Sand Creek Drain Study Proposals