Cook Drain
STATUS OF COOK DRAIN PETITION PROJECT
-
April 9, 2001
Raisin Township Board authorized a resolution for Township Supervisor Larry
Crittenden to sign a Petition for improving the Cook Drain and adding a branch.
-
October 25,
2001 Board of Determination found petition necessary.
-
March 21,
2002 Feller & Finch & Associates, Inc., Consulting Engineers selected to perform
a study on the Cook Drain and adding a branch.
-
April 17,
2003 preliminary plans received from study by Feller & Finch & Associates, Inc.,
Consulting Engineers.
-
2004-2005
petition project evaluated while gravel mining operations were established in
the vicinity of the drain.
-
May 22, 2006 study completed by Feller &
Finch & Associates, Inc., Consulting Engineers.
-
2005 -2006 petition project evaluated while review of proposed plat of Quarry
Heights
was designed.
-
May 2010 open
ditch of the main drain surveyed by Lenawee County Drain Commissioners Office.
-
February 22,
2011 Informational Meeting, 7:00 PM Raisin Charter
Township
Community Center.