Cambridge Lake Level Petition

Large JPEG   DWF [?]

 

STATUS OF PETITION

 

  - Petitions to establish a legal lake level submitted in February 2008 by Russell Pratt.

- Petitions were found valid March 5, 2008.

- Lenawee County Board of Commissioners passed a resolution to start the process of establishing a legal level at Cambridge Lake and delegated authority to the office of the Lenawee County Drain Commissioner on Wednesday March 12, 2008.

- Request for engineering study proposal March 19, 2008.

- Engineering study proposal to be submitted by April 14, 2008.

- Spicer Group, Consulting Engineers selected to perform study on existing structure in June 2008.

- Preliminary study submitted by the Spicer Group in October 2008.

- Informational Meeting on study results December 9, 2008 at Onsted American Legion Hall, Onsted, MI. 

- January 14, 2009 Lenawee County Board of Commissioners Passed a Resolution Authorizing the Lenawee County Prosecutors Office to Petition Lenawee County Circuit Court on Establishing a Legal Lake Level at Cambridge Lake.

- February 4, 2009 Lenawee County Prosecutors Office Provided with Information to Petition Lenawee County Circuit Court.

- April 24, 2009 Circuit Court Petitioned to establish a Legal Lake level at
Cambridge by Lenawee County Prosecutors Office.

- June 29, 2009 the Honorable Margaret M.S. Noe, Circuit Court Judge, order
the Legal Lake Level of Cambridge Lake to be at a Summer Level of 939.70 and
a Winter level of 939.20.

- August 3, 2009 the Honorable Margaret M.S. Noe, Circuit Court Judge Ordered Confirmation of the Assessment District for maintaining the Lake Level at Cambridge Lake.

- November 16, 2009 Advertisement for Bids on Lake Level Control Structure
replacement. Notice of Day of Review of Apportionments.

- December 1, 2009 1:00 PM Bid Opening

- December 7, 2009 at Lenawee County Drain Commissioner's Office, 320
Springbrook Avenue, Suite 102, Adrian, MI. Day of Review of Apportionments

- December 9, 2009 Lenawee County Board of Commissioners Passed Resolution Approving Assessment Roll.

- December 22, 2009 Michigan Department of Environmental Quality Issued
Permit for Replacing the Dam Control Structure at Cambridge Lake. Permit No.
09-46-0033-P.

- January 13, 2010 Notice of Award to low bidder, E. T. MacKenzie Co.,
Contractor for Construction.

- Prepayment of Assessment Due by February 1, 2010.

- February 12, 2010 Bond Bid Opening for Financing of Project.

- February 26, 2010 Pre-Construction Meeting and Notice To Proceed to , E. T.
MacKenzie Co., Contractor for Construction.

- March 1, 2010 Construction Started on Replacement of Lake Level Control
Structure.

- Construction of new structure is substantially complete.  Sluice gate installation scheduled for June 2010 and completion of construction project.

- Construction of new dam completed. Restoration and clean up to be completed.


 

Downloads

Structure Detail Drawing
Part 307, Act 451 of 1994
Advantages & Disadvantages
Duties of County Delegated Authority

Requirements for Cambridge Lake Level Study
Questionnaire packet
Letter sent to Cambridge Lake Property Owners regarding Informational Meeting
Spicer Group presentation of study results from December 9 Informational Meeting
Advertisement for Bids - Lake Level Control Structure
Bid Opening - Tabulation
Notice of Day of Review of Apportionments