STATUS OF CULHANE DRAIN PETITION PROJECT
- July 19, 2006 Ron Francour, 5766 Furman Highway, Clayton, MI 49235, received petition for the Culhane Drain.
- August 9, 2006 petition returned by Ron Francour.
- August 18, 2006 petition signatures found valid.
- October 17, 2006 a Board of Determination determined the Petition to be necessary.
- November 3, 2006 Lenawee County Clerks Office contacted and no appeals filed on Determination of the Necessity of the Petition.
- November 20, 2006 notice to land owners along drain mailed for obtaining information on drainage issues with tile.
- Survey of Drain in May, July, October, & December 2007 & March 2008.
- September 2008 Preparation of Bid Documents and Construction Plans.
- November 21, 2008 Notice of Letting of Drain Contract and Day of Review of Apportionments
- December 10, 2008 1:00 PM Bid Opening at the Lenawee County Drain Commissioner's Office
- December 17, 2008 Day of Review of Apportionments, 9:00 AM - 5:00 PM at the Lenawee County Drain Commissioner's Office
|